BUILDING A HOUSE FOR JULIET
The construction of the children's hospice has been strongly supported by the City of Brno from the very beginning of the project. The land for construction was selected in 2018, and subsequently, collaboration began with the architectural studio Čtyřstěn. From 2018 to 2021, architectural studies, project documentation, and construction documentation were created. The building permit for construction was issued in December 2021.
In 2021, the organization Dům pro Julii, z.ú. entered into a cooperation agreement with the City of Brno, which became the investor for the entire construction. The Dům pro Julii organization will provide the equipment for the House and operate all services. The construction commenced with a symbolic laying of the foundation stone on July 19, 2022. The completion of the construction is planned for the beginning of 2024, with the operation set to begin in mid-2024. The House for Julia will be located in the Kociánka area, within the premises of the Home for the Elderly.